Manufacturing
Manufacturing turns components into finished products. You describe the recipe once, then create a manufacturing order (MO) each time you want to build some units. Aureus reserves the components, schedules the work and records what you produce.
In simple words: Write the recipe, order a build, do the work, get finished goods in stock.
Open the app from the top bar: Manufacturing. It has four menus: Operations, Products, Configurations and Settings. The Work Orders page appears under Operations only after you turn on Work Orders in settings.
Key terms
| Term | Meaning |
|---|---|
| Bill of materials (BoM) | The recipe: which components make one finished product. |
| Component | A product you use up to build another product. |
| Manufacturing order (MO) | One request to build a number of units. |
| Operation | One step of the recipe, such as assembly or packing. |
| Work center | A machine or station that does an operation. |
| Work order | An operation of one MO, to be done at a work center. |
| Lot or serial number | A number that identifies a batch or a single unit. |
The whole flow
text
Product + Bill of Materials → Warehouse steps → Manufacturing order (Draft)
→ Confirm → Plan → Work orders → Produce All → DonePlan and Work orders apply only when Work Orders is on. Warehouse steps are a one-time setup.
| Stage | What happens | Page |
|---|---|---|
| Set up | A goods product and a recipe (Bill of Materials) | Configure a product, Bill of materials |
| Choose warehouse steps | One, two or three steps for stock movement | One step, Two steps, Three steps |
| Order | Create the MO in Draft | Manufacturing orders |
| Confirm | Components are reserved, state Confirmed | Manufacturing orders |
| Plan | Work orders get dates on work centers | Plan and schedule |
| Work | Operators start, pause and finish each step | Work orders |
| Produce | Components are used, finished goods arrive, state Done | Produce and consume |
Settings that open menus
Some menus stay hidden until you switch a setting on. Go to Manufacturing → Settings → Manage Operations.
| Setting | What it turns on |
|---|---|
| Work Orders | The Work Orders menu, Work Centers, Operations, the Work Orders tab on an MO and the Operations tab on a BoM |
| Work Order Dependencies | Steps that wait for other steps |
| Multi Steps Routes (Inventory) | The warehouse Manufacturing steps (two and three steps) |
Where to go next
- Get started: Overview, Manufacturing settings, First steps
- Basic setup: Overview, Configure a product, Bill of materials, One step, Two steps, Three steps, Manufacturing order costs
- Advanced configuration: Overview, Work centers, Operations, Work order dependencies, BoM variants
- Workflows: Overview, Manufacturing orders, Plan and schedule, Work orders, Produce and consume, Lots and serial numbers